Below is the latest view of the development timeline for the new Energy from Waste CHP plant at Runcorn Site, Cheshire.
| Start |
Finish |
Activity |
| |
|
|
May/June 2009 |
September 2010 |
Clearance of development site including relocation of existing Weston Workshops facility to main Runcorn Site |
| |
|
|
June 2010 |
|
Main construction contractor to start on site |
| |
|
|
July 2010 |
December 2010 |
Demolition of existing structures on development site |
| |
|
|
September 2010 |
July 2011 |
Construction of new foundations |
| |
|
|
January 2011 |
January 2012 |
Erection of new structures |
| |
|
|
May 2011 |
February 2012 |
Installation of equipment |
| |
|
|
April 2012 |
September 2012 |
Commissioning of new Energy from Waste CHP plant |
| |
|
|
September 2011 |
February 2012 |
Construction of new rail sidings |
| |
|
|
October 2012 |
November 2012 |
Testing of Energy from Waste CHP plant |
| |
|
|
December 2012 |
|
Energy from Waste CHP plant operational |
Need more information?
If you have any questions about the Local Liaison Forum for the Energy from Waste CHP plant you can contact:
Janet Ward, Public Relations Officer
Telephone: FREEPHONE 0800 052 1190 (answer machine available after normal office hours)
Email: janet.ward@ineos.com